Legal Consequences of Construction Project Delays in Indonesia: A Normative Analysis of Breach, Liability, and Dispute Resolution
DOI:
https://doi.org/10.35671/judex.v2i1.165
Keywords:
Construction Delays, Breach of Contract, Construction Law, Legal ConsequencesAbstract
Construction delays are a recurring problem in the implementation of construction contracts and may disrupt cost, schedule, and the intended benefits of a project. Existing studies cited in this article predominantly examine the causes and performance impacts of delays, while legal discussions tend to address default, liability, or dispute resolution separately. This study therefore examines how Indonesian law qualifies construction delays, allocates responsibility among the parties, determines their legal consequences, and provides mechanisms for resolving resulting disputes. The research employs normative legal research using statutory and conceptual approaches. Primary legal materials comprise the Civil Code, Law Number 2 of 2017 concerning Construction Services, Government Regulation Number 22 of 2020, and relevant contractual provisions, supported by secondary legal literature and prior studies. The analysis shows that a delay does not automatically constitute a breach of contract; its legal characterization depends on its cause, contractual risk allocation, and whether the delay is excusable, non-excusable, compensable, or concurrent. Contractor-caused delays may trigger penalties, damages, termination, and performance-bond encashment, whereas owner-caused or excusable delays may justify extensions of time and, where legally and contractually supported, compensation. The study contributes an integrated legal framework linking delay classification to liability and dispute resolution, emphasizing clearer contractual mechanisms for notice, evidence, time extensions, and allocation of delay risk.
References
Arief, Ediyanto, Sarwono Hardjomuljadi, and Sami'an, Kepastian Hukum Penyelesaian Sengketa Kontrak Konstruksi Melalui Arbitrase. JIHHP: Jurnal Ilmu Hukum, Humaniora Dan Politik, Vol. 5 No. 4, (2025): 3031-49.
Diantha, I Made Pasek. Metodologi Penelitian Hukum Normatif dalam Membenarkan Teori Hukum, Jakarta: Kencana, (2024).
Era Fransiska, Adi Saputro, Sami'an, and Sarwono Hardjomuljadi, Penyelesaian Sengketa Konstruksi Melalui Arbitrase. Jurnal Pendidikan Indonesia, Vol. 6 No. 2, (2025).
Ervianto and Wulfram I, Manajemen proyek konstruksi, Yogyakarta: Penerbit Andi, (2022), p, 184–186.
Fadli, A., and M. Yusuf, Factors Causing Delays in Construction Project Implementation in Indonesia, Construction Engineering Journal, Vol. 12, No. 1, (2023), p. 55.
H.S, Salim. Hukum kontrak: Teori dan teknik penyusunan kontrak, Jakarta: Sinar Grafika, (2021).
Hariadi, Madjumsyah, Sami'an, and Aulia, Penilaian Unsur Wanprestasi Dalam Kontrak Proyek Konstruksi Bumn (Studi Kasus Putusan Mahkamah Agung Nomor 1361 Pk/Pdt/2024). Journal of Syntax Literate, Vol. 11, No. 3, (2026), p.2079.
Hidayat, M. R., and S. Nugroho, Analysis of the Impact of Construction Project Delays on Project Performance, Civil Engineering Journal, Vol. 19, No. 2, (2024).
Iman, Soeharto. Manajemen Proyek dari Konseptual sampai Operasional, Jakarta: Erlangga, (1995).
Kamila, Siti Nur, Rudi Mulyanto, and Etis Cahyaning Putri, Analisis Tanggung Jawab Kontraktor atas Keterlambatan Pekerjaan Konstruksi Menurut Undang-Undang Jasa Konstruksi, AMAR, Vol. 3, No. 2, (2025): 58–69.
Muhaimin, Metode Penelitian Hukum, Mataram: Mataram University Press, (2023).
Nevianti, Nisma Deli. Felicitas Sri Marniati, and Ismail, Kepastian Hukum Kontrak Kerja Konstruksi terkait Wanprestasi Penyedia Jasa dalam Menyerahkan Bangunan Tidak Tepat Waktukepada Pengguna Jasa. CENDEKIA: Jurnal Penelitian dan Pengkajian Ilmiah, Vol. 1, No. 9, (2024): 609–625.
Proboyo, B. Keterlambatan waktu pelaksanaan proyek klasifikasi dan peringkat dari penyebab-penyebabnya. Civil Engineering Dimension, Vol. 1, No. 1, (1999): 46-58. DOI: https://doi.org/10.9744/ced.1.1.pp.%2046-58
Rini, Silfia, Detho Wahyu Saputra, and Yulia Setiani, Penyelesaian Sengketa Proyek Pada Penyedia Jasa Konstruksi Di Kota Pekanbaru. Journal of Infrastructure and Civil Engineering, Vol. 4 No. 2, (2024):73-80.
Sanjaya, Robin Antonius. “Disputes in the Construction Sector in Indonesia,” Jurnal Hukum Lex Generalis, Vol. 6 No. 9, (2025): 1-37.
Santika, S. A. D., & Dilaga, Z. A. Tinjauan Yuridis Terhadap Penaganan Wanprestasi Pada Pengerjaan Proyek Monumen Mataram Metro. Private Law, Vol. 4, No. 2, (2024): 573-581.
Susanti, Dyah Ochtorina and A'an Efendi, Penelitian hukum: Legal Research, Jakarta: Sinar Grafika, (2023).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Rahmayanti

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.